Key facts, with sources
Key facts about the 2026 PMP exam, with PMI sources
| What | 2026 exam | Source |
| Launch date | July 9, 2026 | PMI press release |
| Domain weights | People 33% (was 42%), Process 41% (was 50%), Business Environment 26% (was 8%) | PMI new-exam page |
| Tasks | 26: People 8, Process 10, Business Environment 8 | Outline PDF |
| Approaches | About 40% predictive; the other 60% adaptive/agile and hybrid | Outline PDF |
| Length | 180 questions (170 scored + 10 unscored pretest), 4 hours, two 10-minute breaks | Outline PDF PMP page |
| Order | A case-study section comes first, then the first break; the second break is about midway through the remaining questions. You can't go back to a section after its break. | Outline PDF |
| New themes | AI, sustainability, stakeholder engagement; more focus on outcomes, value and business impact | PMI new-exam page |
| Eligibility | Apprenticeships and training now count; 10-year window for experience | PMI new-exam page |
| Retakes | Up to 3 attempts within your 1-year eligibility period | Outline PDF |
This is an independent summary. PM Professor is not affiliated with PMI. For the rules that apply to you, read PMI's outline.
The three domains and 26 tasks
The outline organizes the exam into three domains. Business Environment holds governance, compliance, change control, issues and risk.
- 33%People
- 41%Process
- 26%Business Environment
People33% of the exam, 8 tasks
- Develop a common vision
- Manage conflicts
- Lead the project team
- Engage stakeholders
- Align stakeholder expectations
- Manage stakeholder expectations
- Help ensure knowledge transfer
- Plan and manage communication
Process41% of the exam, 10 tasks
- Develop an integrated project management plan and plan delivery
- Develop and manage project scope
- Help ensure value-based delivery
- Plan and manage resources
- Plan and manage procurement
- Plan and manage finance
- Plan and optimize quality of products/deliverables
- Plan and manage schedule
- Evaluate project status
- Manage project closure
Business Environment26% of the exam, 8 tasks
- Define and establish project governance
- Plan and manage project compliance
- Manage and control changes
- Remove impediments and manage issues
- Plan and manage risk
- Continuous improvement
- Support organizational change
- Evaluate external business environment changes
How exam day runs
The first break comes after the case-study section. The second comes about midway through the independent questions. Once you take a break, you cannot return to the section before it.
- Case studiesShared scenarios
- Break 110 minutes
- Independent questionsFirst part
- Break 210 minutes
- Independent questionsSecond part
The December 1, 2026 training-hours rule
From December 1, 2026, live training hours count toward PMP eligibility only if the course is from a PMI Authorized Training Partner (ATP), a China REP, or an eligible accredited academic program. Self-paced courses count when they are “Self-paced on-demand training courses including an end-of-course assessment” (PMI wording). Source: PMI Examination Content Outline, July 2026 (PDF).
PM Professor is practice and review, not a 35-hour course, so it does not count toward those hours.
Is the PMP exam based on the PMBOK Guide?
No. PMI says the exam is built from the Examination Content Outline, not organized by the PMBOK Guide, and notes "noticeable differences" between them. The PMBOK Guide 8th Edition was published in November 2025 (pmi.org/standards/pmbok). Study from the outline's tasks and use PMBOK as a reference.
Can I keep using older study materials?
PMI says the "core principles and approaches remain the same." Keep going, but check your practice against the new domain weights, especially Business Environment (now 26%).
Pacing tip (our math, not PMI guidance)
240 minutes divided by 180 questions is about 80 seconds per question. Answer every case-study question before the first break, since you can't go back.
What we don't know yet (and won't guess)
PMI hasn't published exact question counts per section (the "40/70/70" split on Reddit is unconfirmed) or any scoring changes. We'll update this page if PMI does.
Try three new-style questions
Original questions by PM Professor; not real exam items and not from PMI. There are 10 on the PMP practice questions page and 10 more on the PMP practice exam page.
A team member's work quality has dropped over two weeks. What should you do first?
- Give them a formal warning.
- Reassign their tasks.
- Tell the team to review their work.
- Meet privately to understand what changed and offer support.
Show the best answer
Best answer: D Understand the person before you act.
- A. Not this one. Acts before understanding.
- B. Not this one. Acts before understanding.
- C. Not this one. Undermines them publicly.
- D. Best answer. Assess first, with empathy.
Best answer: D Understand the person before you act.
- A. Not this one. Acts before understanding.
- B. Not this one. Acts before understanding.
- C. Not this one. Undermines them publicly.
- D. Best answer. Assess first, with empathy.
Leadership announces a reorganization that will change who approves your budget. What should you do?
- Clarify the new governance with the sponsor and update the plan and stakeholder register.
- Pause the project.
- Ask the team to speed up before it happens.
- Keep following the old approval path.
Show the best answer
Best answer: A When governance changes, your plan changes.
- A. Best answer. Align with the new governance.
- B. Not this one. An overreaction.
- C. Not this one. Doesn't address governance.
- D. Not this one. Risks invalid approvals.
Best answer: A When governance changes, your plan changes.
- A. Best answer. Align with the new governance.
- B. Not this one. An overreaction.
- C. Not this one. Doesn't address governance.
- D. Not this one. Risks invalid approvals.
A problem hit the project that a similar past project also faced. What should you have done, and what now?
- Nothing; projects are unique.
- Blame the earlier PM.
- Review lessons learned from past projects early; now record this one and share it.
- Write it in your personal notes.
Show the best answer
Best answer: C Learn from the past, then share what you learned.
- A. Not this one. Ignores history.
- B. Not this one. Unproductive.
- C. Best answer. Use organizational process assets early, then update them.
- D. Not this one. Doesn't help the organization.
Best answer: C Learn from the past, then share what you learned.
- A. Not this one. Ignores history.
- B. Not this one. Unproductive.
- C. Best answer. Use organizational process assets early, then update them.
- D. Not this one. Doesn't help the organization.
How PM Professor follows the outline
PM Professor is our PMP® exam prep app for iPhone and iPad, now on the App Store. Every question is tagged to its domain and to one of the outline's 26 tasks.
Practice scores do not predict your exam result, and the app does not count toward the 35 training hours.
Try free practice questions
PMP exam changes: common questions
When did the PMP exam change?
July 9, 2026.
What are the new PMP domain weights?
People 33%, Process 41%, Business Environment 26%.
How many questions are on the 2026 PMP exam?
180 (170 scored, 10 pretest), in 4 hours with two 10-minute breaks.
Can I go back to a section after a break?
No. There is no return to a previous section after a break.
Does the new PMP exam cover AI?
Yes, AI is one of the new themes PMI lists.
Do my 35 hours still count after December 1, 2026?
Live training counts only from a PMI ATP, China REP or eligible academic program; self-paced on-demand training courses including an end-of-course assessment also count.
Is the exam aligned to PMBOK 8?
PMI says the exam isn't organized by the PMBOK Guide.
What is the passing score?
PMI publishes no passing score, and PM Professor does not estimate one.
Sources
- PMI, PMP Examination Content Outline, July 2026 (PDF).
- PMI, new PMP exam page.
- PMI, press release on the new exam.
- PMI, Project Management Professional (PMP) Certification.
- PMI, Certification Handbook, revised June 2026 (PDF).
- PMI, How to Meet the PMP 35-Hour Training Requirement.
- PMI, PMBOK Guide, Eighth Edition.