Free PMP® practice exam: 10 scenario questions

Tap an answer to see the best one and why.

Updated November 17, 2026. Sources checked that day. Original questions written by PM Professor in the style of the PMP exam, not real exam items and not from PMI.

People · agile

A new team member keeps missing daily stand-ups and the team is frustrated. What should the project manager do first?

  1. Talk with the team member privately to understand what's going on.
  2. Report it to the team member's functional manager.
  3. Raise it at the next retrospective so the team can decide on a rule.
  4. Remove the team member from the stand-up invite list.
Show the answer

Think like a project manager Find out why before you act.

  • A. Best answer. Understand the cause before acting. It may be a scheduling or onboarding issue.
  • B. Not this one. Escalates before you've tried anything yourself.
  • C. Not this one. Makes a personal issue public before you know the cause.
  • D. Not this one. Ignores the problem and isolates the person.

Think like a project manager Find out why before you act.

Business Environment · change control

A key stakeholder asks you to add a feature mid-project. It looks small. What should you do?

  1. Refuse; scope is baselined.
  2. Ask the team to fit it in during slack time.
  3. Assess the impact, then submit a change request through the change control process.
  4. Add it; it's small and keeps the stakeholder happy.
Show the answer

Think like a project manager Assess the impact, then use the process.

  • A. Not this one. Too rigid. Changes are allowed, they're just controlled.
  • B. Not this one. Unapproved work, even if it looks free.
  • C. Best answer. In a predictive project, changes go through integrated change control after impact analysis.
  • D. Not this one. Scope creep. Small doesn't mean approved.

Think like a project manager Assess the impact, then use the process.

Business Environment · compliance

A new regulation will affect your product's data handling in six months. What should the PM do first?

  1. Ask the sponsor to get an exemption.
  2. Assess the impact on the project with compliance experts and update the risk register and plan.
  3. Wait until the regulation takes effect.
  4. Tell the team to start rework now.
Show the answer

Think like a project manager Analyze first, then plan.

  • A. Not this one. Not the PM's first move, and it assumes non-compliance is an option.
  • B. Best answer. Evaluate the impact, then plan for compliance.
  • C. Not this one. Reactive. You'd lose six months of warning.
  • D. Not this one. Acts before any analysis.

Think like a project manager Analyze first, then plan.

People · conflict

Two senior developers disagree on a technical approach and it's slowing the sprint. What should the PM do?

  1. Pick an approach so work can continue.
  2. Escalate to their functional manager.
  3. Let them work it out; self-organizing teams handle their own conflicts.
  4. Facilitate a discussion so the team weighs both options against the sprint goal and agrees.
Show the answer

Think like a project manager Facilitate. Don't decide for the team.

  • A. Not this one. Takes ownership away from the team.
  • B. Not this one. Escalates too early.
  • C. Not this one. Ignores a conflict that is already hurting delivery.
  • D. Best answer. The PM facilitates. The team decides.

Think like a project manager Facilitate. Don't decide for the team.

Business Environment · risk

A risk you identified earlier has now happened. What should you do?

  1. Implement the planned risk response.
  2. Call an emergency meeting with the sponsor.
  3. Start a new risk analysis.
  4. Add the risk to the risk register.
Show the answer

Think like a project manager If there's a plan, use the plan.

  • A. Best answer. It was identified and planned, so execute the response, then update the register.
  • B. Not this one. Escalates when you already have a plan.
  • C. Not this one. Delays action you've already planned.
  • D. Not this one. It's already there.

Think like a project manager If there's a plan, use the plan.

People · AI

A team member wants to paste customer records into a public AI tool to summarize feedback faster. What should the PM do first?

  1. Let the team member decide.
  2. Approve it; it saves time.
  3. Check the organization's data and AI policies and involve the right stakeholders before deciding.
  4. Ban AI tools on the project.
Show the answer

Think like a project manager Check policy and risk before you say yes or no.

  • A. Not this one. Hands off a decision that carries organizational risk.
  • B. Not this one. Ignores the risk to customer data.
  • C. Best answer. Assess governance and data-privacy risk first.
  • D. Not this one. Throws away value without any assessment.

Think like a project manager Check policy and risk before you say yes or no.

Process · hybrid

Your hybrid project has a fixed regulatory milestone, but the software team works in sprints. The product owner wants to reprioritize the backlog. What do you do?

  1. Block the change; the milestone is fixed.
  2. Let the product owner change anything.
  3. Switch the whole project to predictive.
  4. Support reprioritization as long as items needed for the regulatory milestone stay on track.
Show the answer

Think like a project manager Protect the fixed constraint. Let the rest adapt.

  • A. Not this one. Overly rigid. Only the milestone is fixed.
  • B. Not this one. Ignores the hard milestone.
  • C. Not this one. An overreaction.
  • D. Best answer. Hybrid means respecting fixed constraints while the backlog adapts.

Think like a project manager Protect the fixed constraint. Let the rest adapt.

Business Environment · value

Midway through, market changes mean a planned feature will deliver little value. What should the PM do?

  1. Drop it quietly.
  2. Raise it with the sponsor and stakeholders with a value analysis and recommend a decision.
  3. Ask the team to make it better.
  4. Finish it as planned.
Show the answer

Think like a project manager Outcomes and value come first, and stakeholders decide.

  • A. Not this one. Skips governance.
  • B. Best answer. The decision belongs with stakeholders, and it should be informed.
  • C. Not this one. Doesn't address the value question.
  • D. Not this one. Ignores value.

Think like a project manager Outcomes and value come first, and stakeholders decide.

People · stakeholders

A stakeholder who was supportive has stopped attending reviews. What should you do first?

  1. Reach out to understand their concerns and update the engagement approach.
  2. Send them the meeting notes and move on.
  3. Remove them from the stakeholder register.
  4. Escalate to the sponsor.
Show the answer

Think like a project manager Treat the change as a signal and ask why.

  • A. Best answer. A drop in engagement is a signal. Find out why and adapt.
  • B. Not this one. Passive. The cause is still unknown.
  • C. Not this one. Loses a stakeholder.
  • D. Not this one. Escalates before you've tried.

Think like a project manager Treat the change as a signal and ask why.

Process · quality

An inspection finds defects in a deliverable just before handoff to the customer. What do you do?

  1. Hand it off and fix the defects later.
  2. Blame the vendor.
  3. Hide the defects to keep the schedule.
  4. Analyze the root cause, correct the defects and update the process to prevent repeats.
Show the answer

Think like a project manager Fix the problem and the process behind it.

  • A. Not this one. Risks customer trust.
  • B. Not this one. Unproductive, and the defects are still there.
  • C. Not this one. Unethical. PMI's Code of Ethics expects honesty.
  • D. Best answer. Fix it, then prevent it.

Think like a project manager Fix the problem and the process behind it.

Think like a project manager.

On situational questions, the best answer usually follows this order. It's our teaching heuristic, not a PMI rule.

  1. AssessUnderstand the situation first.
  2. CollaborateWork with the team or stakeholders.
  3. Use the processAct within your plan and authority.
  4. Escalate lastOnly after you've tried.

How the real exam is set up.

180 questions in 4 hours with two 10-minute breaks. Case studies come first, and you can't go back to a section after its break.

Timing tip (our math, not PMI guidance): about 80 seconds per question. For these 10 questions, try a 14-minute timer.

180questions on the real exam
240minutes on the real exam
80seconds per question (our math)
  1. 33%People
  2. 41%Process
  3. 26%Business Environment

Sources: PMI, Examination Content Outline, July 2026 (PDF) and new-exam page.

Practice like this every day

The app has the full study path, and it brings back the ones you miss.

Try 10 more questions

For the method behind these questions, read how to choose when two answers look right. For the exam-day order, see how exam day runs. For a fair comparison of prep options, see PMI Study Hall vs Pocket Prep vs PM Professor.

PMP® practice exam: common questions.

How many questions are on the PMP exam?

180 (170 scored, 10 pretest) in 4 hours, per PMI.

Are these real PMP exam questions?

No. They're original practice questions in the exam's style.

What score do I need to pass?

PMI publishes no passing score, and we don't estimate one.

Is there a free full-length PMP practice exam?

Not on this site. This set has 10 questions. Our comparison page covers options with full-length exams.