Free PMP® practice questions: when two answers look right
The tie-break rule: On situational questions, the best answer usually (1) understands or assesses the situation first, (2) works with the team or stakeholders, (3) then acts within the process, and (4) escalates only after the PM has tried. This is our teaching heuristic, not a PMI rule.
Updated November 17, 2026. Sources checked that day. Original questions written by PM Professor in the style of the PMP exam, not real exam items and not from PMI.
A team member's work quality has dropped over two weeks. What should you do first?
Give them a formal warning.
Reassign their tasks.
Tell the team to review their work.
Meet privately to understand what changed and offer support.
Show the answer
Think like a project managerUnderstand the person before you act.
A. Not this one.Acts before understanding.
B. Not this one.Acts before understanding.
C. Not this one.Undermines them publicly.
D. Best answer.Assess first, with empathy.
Think like a project managerUnderstand the person before you act.
Think like a project managerUnderstand the person before you act.
A. Not this one.Acts before understanding.
B. Not this one.Acts before understanding.
C. Not this one.Undermines them publicly.
D. Best answer.Assess first, with empathy.
Process · agile
Halfway through a sprint, the product owner asks to add an urgent item. What happens?
The PM refuses all changes.
The product owner works with the team; if it can't wait, they negotiate what comes out of the sprint or put it at the top of the backlog for the next sprint.
The sponsor decides.
The team adds it immediately.
Show the answer
Think like a project managerKnow who owns what, then negotiate.
A. Not this one.Not agile.
B. Best answer.The product owner owns the backlog, and the team protects the sprint goal through negotiation.
C. Not this one.Bypasses the roles.
D. Not this one.Silently breaks the sprint commitment.
Think like a project managerKnow who owns what, then negotiate.
Think like a project managerKnow who owns what, then negotiate.
A. Not this one.Not agile.
B. Best answer.The product owner owns the backlog, and the team protects the sprint goal through negotiation.
C. Not this one.Bypasses the roles.
D. Not this one.Silently breaks the sprint commitment.
People · virtual teams
Your team spans three time zones and handoffs keep failing. What first?
Add more status reports.
Require everyone to work the same hours.
Work with the team to agree on overlap hours and a handoff working agreement.
Move work to one location.
Show the answer
Think like a project managerSolve it with the team, not for the team.
A. Not this one.More reporting doesn't fix handoffs.
B. Not this one.Heavy-handed.
C. Best answer.Collaborate on a team agreement.
D. Not this one.Heavy-handed.
Think like a project managerSolve it with the team, not for the team.
Think like a project managerSolve it with the team, not for the team.
A. Not this one.More reporting doesn't fix handoffs.
B. Not this one.Heavy-handed.
C. Best answer.Collaborate on a team agreement.
D. Not this one.Heavy-handed.
Process · procurement
A vendor will miss a contractual delivery date. What should you do first?
Review the contract terms and meet the vendor to understand the cause and recovery options.
Terminate the contract.
Withhold payment.
Find a new vendor.
Show the answer
Think like a project managerStart with the contract and the facts.
A. Best answer.Start with the contract and the facts.
B. Not this one.Drastic before you've assessed anything.
C. Not this one.Drastic before you've assessed anything.
D. Not this one.Drastic before you've assessed anything.
Think like a project managerStart with the contract and the facts.
Think like a project managerStart with the contract and the facts.
A. Best answer.Start with the contract and the facts.
B. Not this one.Drastic before you've assessed anything.
C. Not this one.Drastic before you've assessed anything.
D. Not this one.Drastic before you've assessed anything.
Business Environment · sustainability
The sponsor asks you to consider the project's environmental impact. What's your best step?
Add a line to the closing report.
Delegate it to the facilities team.
Identify sustainability requirements with stakeholders and include them in planning.
Say it's out of scope.
Show the answer
Think like a project managerNew requirements belong in the plan.
A. Not this one.Too late to change anything.
B. Not this one.Hands it off without integrating it.
C. Best answer.Sustainability is a new 2026 theme. Treat it as requirements to plan for.
D. Not this one.Dismisses a sponsor request.
Think like a project managerNew requirements belong in the plan.
Think like a project managerNew requirements belong in the plan.
A. Not this one.Too late to change anything.
B. Not this one.Hands it off without integrating it.
C. Best answer.Sustainability is a new 2026 theme. Treat it as requirements to plan for.
D. Not this one.Dismisses a sponsor request.
People · empowerment
The team asks you how to estimate a user story. What do you do?
Use last project's numbers.
Give them the estimate.
Ask the product owner to estimate.
Facilitate an estimation technique such as planning poker so the team estimates.
Show the answer
Think like a project managerThe people doing the work estimate it.
A. Not this one.Ignores this project's context.
B. Not this one.Takes ownership from the team.
C. Not this one.Takes ownership from the team.
D. Best answer.In agile, the people doing the work estimate. The PM facilitates.
Think like a project managerThe people doing the work estimate it.
Think like a project managerThe people doing the work estimate it.
A. Not this one.Ignores this project's context.
B. Not this one.Takes ownership from the team.
C. Not this one.Takes ownership from the team.
D. Best answer.In agile, the people doing the work estimate. The PM facilitates.
Process · schedule
A critical-path task is running late. What first?
Tell the sponsor the project will be late.
Analyze options like fast-tracking or crashing and their impact, then act within your authority.
Add overtime for everyone.
Remove scope.
Show the answer
Think like a project managerWeigh the options before you commit.
A. Not this one.Reports before you've tried anything.
B. Best answer.Analyze schedule compression options first.
C. Not this one.One option, chosen without analysis.
D. Not this one.Changes scope without approval.
Think like a project managerWeigh the options before you commit.
Think like a project managerWeigh the options before you commit.
A. Not this one.Reports before you've tried anything.
B. Best answer.Analyze schedule compression options first.
C. Not this one.One option, chosen without analysis.
D. Not this one.Changes scope without approval.
Business Environment · governance
Leadership announces a reorganization that will change who approves your budget. What should you do?
Clarify the new governance with the sponsor and update the plan and stakeholder register.
Pause the project.
Ask the team to speed up before it happens.
Keep following the old approval path.
Show the answer
Think like a project managerWhen governance changes, your plan changes.
A. Best answer.Align with the new governance.
B. Not this one.An overreaction.
C. Not this one.Doesn't address governance.
D. Not this one.Risks invalid approvals.
Think like a project managerWhen governance changes, your plan changes.
Think like a project managerWhen governance changes, your plan changes.
A. Best answer.Align with the new governance.
B. Not this one.An overreaction.
C. Not this one.Doesn't address governance.
D. Not this one.Risks invalid approvals.
People · ethics
A stakeholder offers you a gift card to prioritize their feature. What do you do?
Prioritize their feature without the gift.
Politely decline and keep prioritizing by the agreed process; follow your organization's policy on reporting.
Accept it; it's small.
Accept but tell no one.
Show the answer
Think like a project managerKeep the process fair, whatever is on offer.
A. Not this one.Bends priorities anyway.
B. Best answer.PMI's Code of Ethics stresses fairness and avoiding conflicts of interest.
C. Not this one.A conflict of interest at any size.
D. Not this one.A conflict of interest, and hiding it makes it worse.
Think like a project managerKeep the process fair, whatever is on offer.
Think like a project managerKeep the process fair, whatever is on offer.
A. Not this one.Bends priorities anyway.
B. Best answer.PMI's Code of Ethics stresses fairness and avoiding conflicts of interest.
C. Not this one.A conflict of interest at any size.
D. Not this one.A conflict of interest, and hiding it makes it worse.
Process · lessons learned
A problem hit the project that a similar past project also faced. What should you have done, and what now?
Nothing; projects are unique.
Blame the earlier PM.
Review lessons learned from past projects early; now record this one and share it.
Write it in your personal notes.
Show the answer
Think like a project managerLearn from the past, then share what you learned.
A. Not this one.Ignores history.
B. Not this one.Unproductive.
C. Best answer.Use organizational process assets early, then update them.
D. Not this one.Doesn't help the organization.
Think like a project managerLearn from the past, then share what you learned.
Think like a project managerLearn from the past, then share what you learned.
A. Not this one.Ignores history.
B. Not this one.Unproductive.
C. Best answer.Use organizational process assets early, then update them.